Montana gas power plant can resume construction, judge rules

| June 9, 2023 10:35 AM

By MATTHEW BROWN

Associated Press

BILLINGS, Mont. — NorthWestern Energy will resume construction of a natural gas power plant along Montana's Yellowstone River following a two-month delay, a company spokesperson said Friday, after a state judge revived a pollution permit for the project despite lingering concerns over its climate-changing emissions...