I-90 lane closures planned for this week
POST FALLS - Motorists on Interstate 90 in Post Falls can expect one lane to close westbound on Thursday night into Friday and one eastbound lane to close Friday night into Saturday as crews begin the next stage of work on the Greensferry overpass.
The closures, which will be from 8:30 p.m. to 5 a.m., will allow crews to remove concrete forms and overhang brackets on the bridge.
The contractor will install final wall panels for the southern ramp and begin pouring sidewalk and wall cap for the northern ramp.
Roadway work is expected to begin along the Greensferry local access lane connecting to Schneidmiller Avenue and the new turn lane on Seltice Way just east of Greensferry Road.
In addition, installation of a traffic signal at Seltice Way and Greensferry Road is anticipated to begin today.
Work on the overpass began in late 2014 and is expected to be completed in mid-November. Landscaping will be done in the spring.
The Post Falls Urban Renewal Agency is funding the $15 million project. The contractor is Ralph L. Wadsworth Construction.
For questions or concerns regarding the overpass, call 755-1862 or email [email protected].